Sindh High Court
Dadabhoy Foundation & another (Appellant) VS K. B. C. A. & others (Respondent)
Outcome The appeal was dismissed along with pending applications, and contempt proceedings were left to continue before the learned Single Judge in accordance with law.
- Case
- H.C.A 242/2018
- Type
- Civil Appellate Jurisdictions
- Bench
- Chief Justice Mr. Justice Muhammad Shafi Siddiqui, Mr. Justice Jawad Akbar Sarwana
- Length
- 3 pages
The appeal concerned whether the appellants could shift containers and carry out construction on the disputed plot despite an earlier status quo order. The Sindh High Court held that the status quo order bound both parties, that the later JM order did not permit construction, and dismissed the appeal.
The full analysis is free with a Lawzo account
- The background of the case
- 3 issues before the court
- 3 holdings, each with the court's own words and page
Takes a few seconds with Google. You'll come straight back here.
Written by AI from the judgment's text and may miss nuance. Rely on the full judgment below and the court's official copy. Court's own note: The order passed in JM has not given a license to carry on construction in violation of status quo order. In fact it restrained the parties from raising construction. Even the permission claimed from Sindh Building Control Authority is of no avail in presence of status quo order and the matter being subjudice.
Full judgment
Official copyIN THE HIGH COURT OF SINDH AT KARACHI
Present:
Mr. Justice Muhammad Shafi Siddiqui Mr. Justice Jawad Akbar Sarwana
High Court Appeal No. 242 of 2018
Dadabhouy Foundation & another Versus Karachi Building Control Authority & others
Date of Hearing: 12.12.2023
Appellants: Through Mr. Tariq Memon Advocate.
Respondent No.2&5: Through Qazi Abdul Hameed Siddiqui, Deputy Attorney General.
Respondent No.4: Through Mr. Sandeep Malani, Assistant Advocate General.
Respondent No.6: Through Mr. Muhammad Najeeb Jamali Advocate.
JUDGMENT
Muhammad Shafi Siddiqui, J.- Record shows that suit No.74/2003 was being taken up along with suit No.891/2003. The appellants have impugned order dated 15.08.2018 passed by learned Single Judge in Suit No.891 of 2003 whereby learned Single Judge has directed plaintiffs/appellants to remove the construction or the placement of the containers at site, within a period of ten days, failing whereof Nazir was directed to remove the same at the cost of the alleged contemnors/appellants. Prayer of the two suits is reproduced for a comparative analysis:-
Suit No.74/2003 Suit No.891/2003 i. Declaration that the plaintiffs a. Declare that the amenity plot are entitled to use the property bearing bearing No.SNPA-17-B with No.SNPA-17-B, near Hill Park, Karachi constructed building thereon (which Cooperative Housing Society Union, was previously known as waseem Karachi, for establishing and running toosy Hospital) Survey No.35-P/1 university/ educational institution. measuring 3700 Sq. yards, situated at Karachi Co-operative Housing Society
ii. Permanent injunction restraining Union Limited Block No.3, KARACHI, is the defendants from stopping the an amenity plot meant for the use of plaintiffs from using the aforesaid a hospital and the Defendant No.3 has premises as university/ educational illegally converted the same into a institution or interfering with their use commercial education institution. in any manner whatsoever.
b. Declare that the Defendant iii. Cost of the Suit. No.3 has committed violations of the law and rules concerning building iv. Any other relief which this control as well as educational Honourable Court may deem fit and institutions/ universities. proper under the circumstances of the case. c. Direct the Defendant No.2 to take immediate action against Defendant No.3 in accordance with law and rules.
d. Permanently restrain the Defendant No.4 from transferring the said property in favour of Defendant No.3 or in that matter in favour of any person/ institution in violation of law.
e. Permanently restrain the Defendant No.5 and 6 from granting Charter/permission to the Defendant No.3 to run university/ educational institution in violation of law.
f. Cost of the suit.
g. Other reliefs as deemed appropriate during course of the suit.
2.Heard the counsels and perused record.
3.Previously an injunctive order was passed in suit No.74/2003 on 21.01.2003 whereby the “parties” were required to maintain status quo.
The status of the subject plot of the suits was disputed between parties.
The plot is situated near Hill Park whereas status of the plot was claimed to be either educational and/or meant for hospital and so it is yet to be determined in the proceedings. However, learned Single Judge on 21.01.2003 was pleased to direct the parties to maintain status quo. It is not disputed, in fact admitted by Mr. Tariq Memon Advocate, that shifting of the “containers” took place subsequent to the said order of “status quo” and it is appellants’ case that this “status quo” order was effective only for the defendants/respondents and not appellants.
Counsel for appellants has also referred to an order passed in JM 3 of
2004, which arises out of one of the suits in respect of an order passed therein, wherein construction raised at that time, being contemptuous, was ordered to be considered/ adjudged at the time of disposal of the suit. However, this recent development of shifting of containers, was subsequent to the order dated 29.10.2010 passed in JM 3 of 2004 and order of status quo dated 21.01.2003. Even otherwise, the order passed in JM has not given a license to carry on construction in violation of status quo order. In fact it restrained the parties from raising construction. Even the permission claimed from Sindh Building Control Authority is of no avail in presence of status quo order and the matter being subjudice.
4.Apparently and undisputedly, as could be seen in undisputed photographs placed on record of this appeal, the containers were shifted for a purpose as an alternate construction, which in any case is violative of status quo order. Containerized structure could not defeat the purpose of status quo order to be maintained by “both parties” and not as interpreted in the order of J.M 3/2004.
5.We are more concerned of the violation of the status quo order, which was passed and/or directed against both the parties and apparently violated and hence it was ordered to be removed. Thus, in these circumstances, appeal merits no consideration and the same is accordingly dismissed along with pending applications. Insofar as contempt proceedings are concerned, they may continue to be proceeded in accordance with law and be taken to its logical end by the learned Single Judge, without being influenced by any of the observations here.
Judge
Judge Ayaz Gul
Text extracted from the court's PDF and reflowed for reading. The court's official copy is authoritative.
Similar judgments
Closest in subject matter, from every court in the library.
- Sindh High Court · 2024 SHC KHI 669 · 8 Oct 2024 Muhammad Yahya and Others (Appellant) VS Province of Sindh & Others (Respondent)
- Sindh High Court · 2021 SHC KHI 534 · 10 Nov 2021 Muhammad Saleem Asar & Ors (Appellant) VS Karachi Building Control Authority & Or (Respondent)
- Sindh High Court · 2024 SHC KHI 989 · 8 Oct 2024 Muhammad Yahya and Others (Appellant) VS Cutchi Memon Co. Housing Society Ltd & Others (Respondent)
- Sindh High Court · 2023 SHC KHI 246 · 31 Aug 2023 Government of Sindh (Appellant) VS Mrs. Hailey Vincent D Abreo & others (Respondent)
- Sindh High Court · 2024 SHC KHI 1305 · 18 Dec 2024 Najibul Haq & Ors (Appellant) VS M/s. Works Coop. Housing Society and Ors (Respondent)